Upper Trinity
Regional Water District


900 North Kealy Street
P.O. Box 305
Lewisville, Texas 75067
(972) 219-1228
www.utrwd.com

Get a Map

 

Upper Trinity's Field Office is now open!

We're located at 10910 State Highway 34, Ladonia, TX 75449.

If you have questions, please call us at 903-367-7008.

 

 

With Vision and courage, we plan.

With cooperation and committment, we serve.

 

 

 

 

 

Content for class "clearfloat" Goes Here

PROJECT COMPONENTS

Dam and Spillways

  • Status: Design 60 percent complete

  • Engineer: Freese & Nichols

  • Construction Procurement: Anticipated July-August 2020

  • Procurement/Contracting Method: Competitive Sealed Proposals

  • Scope Includes: Dam; spillway; emergency spillway; outlet/intake structure; intake valves, piping and structure; dam and borrow area clearing

 

Roads and Bridges

  • Status: Negotiating TxDOT Advanced Funding Agreement & Fannin County Agreement

  • Design and Construction Procurement: Anticipated early 2020

  • Procurement/Contracting Method: Progressive Design Build

  • Scope Includes: SH 34 & FM 1550 relocations; improvements; adjustments and terminations of county roads; demolition of four bridges; removal of abandoned paving on SH 34, FM 2990 and FM1550; and clearing in roadway construction areas.

  • Roadway Fact Sheet

  • Lake Ralph Hall Roadway Relocations Industry Presentation (February 24, 2020)

  • Received Statement of Qualifications on April 23, 2020; anticipate award at August Board of Directors meeting

 

Aquatic Mitigation

  • Status: Mitigation Plan finalized and includes preliminary design of stream and wetland mitigation

  • Mitigation Design, Construction and Monitoring: Procurement anticipated Spring 2020

  • Procurement/Contracting Method: Competitive Sealed Proposals/Full Service Provider

  • Scope Includes: Final design, construction, monitoring, maintenance, and adaptive management of aquatic mitigation through acceptance by USACE

  • Request for Qualifications: for Full Service Provider in regards to required mitigation due July 10, 2020 See request posted on Civcast

 

Clearing and Demolition

  • Status: Clearing and demolition requirements not yet defined

  • Design Procurement: Spring 2020

  • Construction Procurement Anticipated: Early 2021

  • Procurement/Contracting Method: CMAR or Conventional Design-Bid-Build

  • Scope Includes: Clearing and Demolition

 

Conveyance Elements

  • Status: Conceptual design completed for pipeline alignment, system hydraulics, balancing reservoir site & pump station site

  • Preliminary Design: General Engineering: LAN

    • -- Scope Includes: Finalizing pipeline alignment, ROW survey and instrument preparation, mapping, preliminary design for pump station, balancing reservoir, and flow control station at Irving Pipeline, system hydraulic design (including surge), controls conceptual design, coordinate final design
  • Pipeline Final Design: Procurement anticipated Spring 2021

    • -- Procurement/Contracting Method: RFQ
    • -- Scope Includes: Developing plans and specifications for pipeline procurement and Construction
  • Pump Station Final Design: Procurement anticipated Spring 2021

    • -- Procurement/Contracting Method: RFQ
    • -- Scope Includes: Final design of station, System SCADA, Irving Control Station
  • Balancing Reservoir Final Design: Procurement anticipated Spring 2021

    • -- Procurement/Contracting Method: RFQ
    • -- Scope Includes: Final design of balancing reservoir, access roads and on-site piping
  • Pipeline Construction: Procurement anticipated Fall 2022

    • -- Procurement/Contracting Method: CMAR or Conventional Design-Bid-Build
    • -- Scope Includes: Pipeline construction
  • Pump Station Construction: Procurement anticipated Fall 2022

    • -- Procurement/Contracting Method: CMAR or Conventional Design-Bid-Build
    • -- Scope Includes: Pump Station and Control Station for Irving Pipeline
  • Balancing Reservoir Construction: Procurement anticipated Fall 2022

    • -- Procurement/Contracting Method: CMAR or Conventional Design-Bid-Build
    • -- Scope Includes: Balancing reservoir and access roads, on-site piping

 

Support Facilities

  • Status: Site for Lake Headquarters selected; site for operations/maintenance near dam tentatively selected; amenities sites and scope not defined

  • Facilities Design: Procurement anticipated Spring 2021

    • -- Procurement/Contracting Method: RFQ
    • -- Scope Includes: Programming and design for Lake Headquarters, operations/maintenance facilities, amenities
  • Facilities Construction: Procurement anticipated Spring 2022

    • -- Procurement/Contracting Method: Competitive Sealed Proposals/Conventional Design-Bid-Build
    • -- Scope Includes: Lake Headquarters and operations/maintenance facilities

 

Program Support

  • Status: Program Services not yet initiated

  • Procurement Anticipated: Early 2020

  • Procurement/Contracting Method: Request for Proposals/Professional Services

  • Scope Includes: Supporting UTRWD’s management of Lake Ralph Hall program and capital program capabilities with quality assurance laboratory, program maintenance deployment, miscellaneous planning, design and engineering services, inspection and other construction management staff augmentation.

 

PROJECT SCHEDULE

(click schedule to view a larger version)

project schedule

 

For contracting opportunities, please visit: https://www.civcastusa.com/

 

Contact Us:

For more information on contracting opportunities, please contact: